The property before conversion...
First erect some scaffolding...
Order some materials...
Install a fire escape window. Now most materials and waste can be brought in and out through this window and the rest of the house is not disturbed...
Next a new floor and essential structural work...
Next we construct a new dormer. All of the work in this section is done in one day and the dormer is weatherproof before we leave...
Tiles are added to the new dormer...
Then windows and fascias...
The dormer completed...
Now more structural work inside after the dormer work is completed...
Partitioning the space...
Insulation, insulation, insulation...
Plumbing and electrics...
And finally the stairs...
The finished conversion. From empty attic to two bedrooms and a bathroom in eight to ten weeks...
|